§ 4. Catch basins, inlets, headwalls and manholes.  


Latest version.
  • A.

    Size: Sizing of these facilities must be approved by the city engineer in accordance with the overall design capacity for stormwater drainage systems.

    B.

    Location: Catch basins will be required every 300 feet where there is a tangent of 600 to 1,000 feet or more in length with a six percent grade or more or placed at the discretion of the engineer.

    At the intersection of streets, catch basins will be located at the beginning of the radius and not in the middle of the radiuses.

    The number and location of catch basins will be determined by the city engineer.

    C.

    Headwalls: The design and construction of headwalls, to include the material used in the placement locations, shall be subject to approval by the city engineer.

(Ord. of 8-3-81, § R)